Trading platforms network replacement


The Trading Networks Project aims to replace ageing network infrastructure, supporting ASX Trade and ASX 24 to deliver greater reliability, scalability and performance. 

This modernisation includes upgrading core connectivity, hardware and software platforms, as well as implementing enhanced security and resilience measures. The project will improve network capacity, speed and stability for trading participants, reduce latency and provide a future-proof architecture to meet evolving technology and regulatory requirements.

Latest updates

Saturday 15 November 2025

On Saturday 15 November (ALC) and Saturday 29 November (SDC) ASX completed upgrades to the infrastructure that provides aggregation for incoming network connections from participants using ASX 24 and ASX Trade gateways located at their Sydney sites. This is a hardware upgrade no impact is expected to trading participants and there is no participant testing required.

 

Saturday 13 September 2025

On Saturday 13 September 2025, ASX successfully completed the replacement of the ASX Trade ITCH switch. Following the implementation, ASX ITCH customers conducted testing without any issues. The market opened smoothly on Monday, marking the successful delivery of this critical infrastructure upgrade.

 

Trading platforms network replacement timeline

There are three phases to replace the ASX 24 network.

PhaseDescriptionTimeline
ASX Net GlobalReplace Arista switches used from (i) Sydney and regional customer sites for point-to-point connections (ASX to customer premises); (ii) customer points of presence in Singapore, Chicago and Hong Kong.Q3 2025 - Q4 2025
ASX Net Trading WANReplace edge routers customer’s premises used to connect to the trading application, in preparation for server gateway decommission.Q4 2025 - Q1 2027
Co-locationReplace server hardware (cabling and Arista switches) for participants with connections in the Australian Liquidity Centre (ALC). This is planned to be delivered as a greenfields environment, completely segregated from the existing platform connectivity, and will require new physical cross connects for the ASX 24 replacement application.Beginning Q3 2026

 

Engagement forums and resources

Upcoming engagement

EngagementDateAgenda
ASX 24 Marketing Working Group #3Tuesday 24 March 2026
  • Vendor selection
  • Platform features
  • Timeline update
  • Engagement Plan
  • Next steps for cusomters

If you would like to participate in this working group, please contact Futures@asx.com.au.


Past engagement

DatePresentation materialRecording
Tuesday 26 August 2025Presentation slidesSession recording
Friday 14 March 2025Presentation slides Session recording
Friday 27 September 2024Presentation slidesSession recording
Friday 14 June 2024Presentation slidesSession recording
Friday 1 March 2024Presentation slidesSession recording

 

Trading platforms network replacement documentation

All technical documentation will be published on ASX Online.

Communication archive

Date of publicationDescriptionType
1 November 2026ASX Net Trading WAN CPE upgradeMarket notice
13 August 2025ASX Trade ITCH colocation network device refresh – cutover date and participation requirementsMarket notice
30 June 2025ASX Trade network refreshMarket notice
30 April 2025Technology upgrade releases - April 2025TURN notice
10 April 2025ASX Trade – ITCH network device refreshMarket notice
15 February 2025Frequently asked questionsFAQs
5 February 2025ASX 24 Market Working Group - February 2025Presentation material
5 February 2025ASX 24 Market Working Group - February 2025 Webinar recording
5 December 2024ASX Technical and Operational Forum 2024Presentation material
5 December 2024ASX Technical and Operational Forum 2024 Webinar recording